1. A is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
Ans:27 days.
Sol: (A’s 1 day’s work): (B’s 1 day’s work) = 2:1.
(A + B)’s 1 day’s work = 1/18.
Divide 1/18 in the ratio 2:1.
Therefore A’s 1 day’s work = (1/18 * 2/3) = 1/27.
Hence, A alone can finish the work in 27 days.
——————————————
2. 2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work?
Ans: 12 ½ days.
Sol: Let 1 man’s 1 day’s work = x and 1 boy’s 1 day’s work =y.
Then, 2x+3y=1/10 and 3x+2y=1/8.
Solving, we get: x=7/200 and y=1/100.
Therefore (2 men +1 boy)’s 1 day’s work = (2*7/200 + 1*1/100) = 16/200 = 2/25.
So, 2 men and 1 boy together can finish the work in 25/2 =12 ½ days.
——————————————
3. A and B can do a piece of work in 12 days ; B and C can do it in 20 days. In how many days will A, B and C finishes it working all together?
Also, find the number of days taken by each to finish it working alone?
Ans:60 days
Sol: (A+B)’s one day’s work=1/12; (B+C)’s one day’s work=1/15 and (A+C)’s one day’s work=1/20.
Adding, we get: 2(A+B+C)’s one day’s work = (1/12+1/15+1/20)=1/5.
Therefore, (A+B+C)’s one day’s work=1/10.
Thus, A, B and C together can finish the work in 10 days.
Now, A’s one day’s work
= [(A+B+C)’s one day’s work] – [(B+C)’s one day’s work]
= 1/10-1/15)
= 1/30.
Therefore, A alone can finish the work in 30 days.
Similarly, B’s 1 day’s work = (1/10 -1/20) = 1/20.
Therefore, B alone can finish the work in 20 days.
And, C’s 1 day’s work= (1/10-1/12) = 1/60.
Therefore, C alone can finish the work in 60 days.
——————————————
4. Two men A and B working together can dig a trench in 8 hrs while A alone can dig it in 12 hrs. In how many hours B alone can dig such a trench?
Ans:24hours.
Sol: (A+B)’s one hour’s work =1/8, A’s one hour’s work =1/12
Therefore, B’s one hour’s work = (1/8-1/12) =1/24.
Hence, B alone can dig the trench in 24 hours.
——————————————
5. If 20 men can build a wall 56m long in 6 days, what length of a similar wall can be built by 35 men in 3 days?
Ans. Length=49m.
Sol: Since the length is to be found out, we compare each item with the length as shown below.
More men, more length built (Direct).
Less days, less length built (Direct).
Men 20:35 :: 56: x
Similarly, days 6:3 :: 56: x.
Therefore, 20*6*x= 35*3*56 or x= 49.
Hence, the required length= 49m.
——————————————
6. A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
Ans.81
Sol: Remaining work = 1-4/7 =3/7.
Remaining period = (46-33) days =13 days.
Less work, less men (direct)
Less days, more men (indirect).
More hours per day, less men (indirect)
Therefore, work 4/7:3/7 ::117/x
Days 13:33 :: 117/x
Hrs/day 9:8:: 117/x
Therefore, 4/7*13*9*x= 3/7*33*8*117 or x= 198.
Therefore, additional men to be employed =(198-117) =81.
——————————————
7. X alone can do a piece of work in 15 days and Y alone can do it in 10 days. X and Y undertook to do it for Rs. 720. With the help of Z they finished it in 5 days. How much is paid to Z?
Sol. In one day X can finish 1/15th of the work.
In one day Y can finish 1/10th of the work.
Let us say that in one day Z can finish 1/Zth of the work.
When all the three work together in one day they can finish 1/15 + 1/10 + 1/Z = 1/5th of the work.
Therefore, 1/Z = 1/30.
Ratio of their efficiencies = 1/15: 1/10: 1/30 = 2: 3: 1.Therefore Z receives 1/6th of the total money.
According to their efficiencies money is divided as 240: 360: 120.
Hence, the share of Z = Rs. 120.
——————————————
8. A group of workers can do a piece of work in 24 days. However as 7 of them were absent it took 30 days to complete the work. How many people actually worked on the job to complete it?
Solution:
Let the original number of workers in the group be ‘x’
Therefore, actual number of workers = x-7.
We know that the number of manhours required to do the job is the same in both the cases.
Therefore, x (24) = (x-7).30
24x = 30x - 210
6x = 210
x = 35.
Therfore, the actual number of workers who worked to complete the job = x - 7 = 35 -7 = 28.
0 comments ↓
There are no comments yet...Kick things off by filling out the form below.
Leave a Comment